Concrete floor slab construction process includes erection of formwork, placement of reinforcement, pouring, compacting and finishing concrete and lastly removal of formwork and curing of concrete slab. Table of Contents Concrete Floor Slab Construction Process 1. Assemble and Erect Formwork for Slab 2. Prepare and Place Reinforcement for Slab 3. Pour, Compact and Finishing Concrete Floor Slab 4. Curing Concrete and Remove Formwork Concrete Floor Slab Construction Process Assemble and Erect Formwork Prepare and Place Reinforcement Pour, Compact and Finish Concrete Curing Concrete and Remove Formwork 1. Assemble and Erect Formwork for Slab The formwork shall be designed to withstand construction loads such as fresh concrete pressure and weight of workers and operators and their machines. Guide to Formwork for Concrete ACI 347-04 shall be followed for the design of formworks. Moreover, there are various construction aspects that need to be considered during...